Well, it is getting done - but it is sort of in this "stew" right now! Today I had to go pick up toilets. I think we have everything pretty much lined up to get the plumbing connections done this weekend. We got started just after lunch - and the rain gave us a bit of trouble - but we built a saw bench on the back porch.
We got all but two of the window casings installed. Of the two left, we have the box built for one- and we are out of trim for both. So, 6 of 8 windows look incredibly better! More caulking and nail-punching to do!
The marble thresholds we had to get to transition between tile and carpet are installed - along with a tad of tile work! Robert did that in about 45 minutes tonight.
We have all but one door up - the other door is just not here yet - and we have to get door-knobs and door stops - SOON.
Thursday's (tomorrow's) list!
We are going to work on the casings for our large openings in the house.
The cabinet people are supposed to come back to finalize the cabinets - mainly putting a countertop on the island.
The marble people are coming to install the poured vanity in the master bath.
Not sure about the glass door guy!
We may get some plumbing work done Thursday evening.
We will install baseboard wherever we can.
When time permits (and it may not) I will work on nail punching and filling nail holes in trim.
As tired as I am of working out there this week, I plan to stay late tomorrow working on the trim.